Hawaii County, HI
Home MenuOur County » Legislative » Office of the County Auditor » Audit Reports
Department of Public Works Contracts, Change Orders, and Supplements
We have conducted a performance audit of the Department of Public Work’s construction contracts, change orders, and supplemental agreements and found gaps in DPW’s management and operational practices.
The purpose of this engagement was twofold: First, to verify the effective management of construction and consultant contracts to minimize unnecessary changes and help ensure on-time and on-budget project deliverables. Secondly, to verify compliance of construction and consultant contracts with applicable regulations.
This audit is not the first conducted by the Office of the County Auditor (OCA) for this department on this subject matter. In 2008, OCA, formerly the Office of the Legislative Auditor, performed a limited-scope performance audit on CIP Contracts, Change Orders, and Supplements for FY2006-2007. The audit identified several areas for improvement. Due to the passage of time and significant operational changes, we decided to conduct a separate audit from the initial one. However, we will refer to its results as they relate to our findings since specific key issues have persisted for at least the last 15 years. Some of those critical issues include:
Auditor Note: It is crucial to comprehend the historical record as it provides context, history, and reasoning for the current audit. Additionally, it emphasizes the importance of prioritizing longstanding issues that have been neglected for a significant period. Our findings are exclusively derived from the information we have independently obtained, without reliance on the previous audit report.
Management is responsible for the performance of its operations, including the design, implementation, and monitoring of programs and activities. Management is also responsible for establishing and maintaining internal controls and performance measurement systems that enable the department to achieve its objectives.
Our responsibility is to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions. We believe that our audit provides a reasonable basis for findings and conclusions, which are expressed solely for the purpose of this report and should not be used for any other purpose.
Based on the evidence, the performance of DPW’s Engineering Division was effective in achieving its objectives during the audit period, while the Building Division continues to face significant challenges.
Based on our audit findings, we offer the following seven recommendations:
Complete Contract Specifications
1. We recommend the Building Division allocate more time for collaboration between the clients and consultants during the project's design phase. The Building Division should also review its contract specifications to ensure that they include all necessary details to decrease the need for change orders. Additionally, inspections should be enhanced to identify issues associated with aging facilities.
Conduct Onsite Inspections Regularly
2. We recommend that the Building Division hire construction inspectors and/or outsource to contract inspectors, requiring them to report directly to the County’s Building Division.
Certified Payroll and Invoice Discrepancies
3. We recommend Building Division develop and document a systematic way of central processing and managing certified payroll and invoice documentation.
Use Project Management Software
4. We recommend DPW acquire project management software to improve the tracking and management of their projects.
Establish Written Policies and Procedures
5. We recommend the DPW Administration Division Contract Group, Building Division, and Engineering Division’s Inspection group create or update policies and procedures for their work processes. Elements should include but not be limited to:
- A standard format
- Distribution
- Version control
- Annual review/updates
Develop Lessons Learned Process
6. We recommend DPW develop a lessons-learned process where all project team members review and discuss:
- What went right
- What went wrong
- What needs to be improved
Following the meeting, the project manager or their designee should draft a report, disseminate it, and memorialize the outcomes to be referenced in future projects. The report should include, but not be limited to:
- Strengths
- Weaknesses/challenges
- Questions such as: Should we avoid or replicate this process in the future? If so, how can this be done, and how will it benefit?
Increase Workforce Outreach
7. We recommend the Building and Engineering Divisions work with the Department of Human Resources to recruit and retain positions consistent with the merit principle (HRS §76-1), including but not limited to evaluating:
- Employee benefits
- Competitive compensation packages
- Career development and growth opportunities
- Organizational culture
- Communication and transparency
- Employee mental health
- Recruitment efforts
Additionally, we recommend the Building Division work with Human Resources to review the Project Coordinators' position description and make changes where necessary.
Conclusion
Complete Contract Specifications
1. Completing contract specifications can help identify and address any unaddressed concerns and requirements before the construction phase begins. Additionally, identifying existing issues that may arise within aging County facilities may help to avoid costly change orders during construction.
Conduct Onsite Inspections Regularly
2. Hiring construction inspectors or contract construction inspectors who report directly to the County’s Building Division increases the assurance that County assets are being protected.
Certified Payroll and Invoice Discrepancies
3. Processing, managing, and centrally storing documentation for invoices and certified payroll will ensure all appropriate information has been processed and documented in the event the Building Division’s Design and Engineering group needs to access and retrieve information.
Use Project Management Software
4. Implementing this recommendation will provide DPW management and project teams the opportunity to track projects at the aggregate and project level. It would also provide the management teams with the ability to provide additional management oversight.
Establish Written Policies and Procedures
5. Implementing policies and procedures will provide a logical way to:
- Manage projects
- Maintain consistency across projects
- Manage documentation
- Assume responsibility for projects that were started by other staff members.
- Use policies and procedures can also be used for training and guidance of new staff.
Develop Lessons Learned Process
6. The benefits of implementing this Recommendation are that the project teams can identify their strengths and weaknesses and use the information gained from the lessons-learned process to continuously improve their weaknesses and strengthen areas where they are already performing well.
Increase Work Force Outreach
Recruiting and retaining positions consistent with the merit principle enhances the overall value perceived by employees in their employment with the County.
We thank the Department of Public Works for their cooperation and efforts to improve internal controls over their process for contracts, change orders, and supplemental agreements.
To improve government accountability and ensure audit recommendations are implemented or resolved, we will continuously monitor the status of pending recommendations using our remediation tracker. To view the status, visit us at: https://www.Hawaiʻicounty.gov/our-county/legislative/office-of-the-county-auditor.
Mission
It is our mission to serve the Council and citizens of Hawaiʻi County by promoting accountability, fiscal integrity, and openness in local government. Through performance and/or financial audits of County agencies and programs, the Office of the County Auditor examines the use of public funds, evaluates operations and activities, and provides findings and recommendations to elected officials and citizens in an objective manner. Our work is intended to assist County government in its management of public resources, delivery of public services, and stewardship of public trust.
Audit Authority
Hawaiʻi County Charter §3-18 establishes an independent audit function within the Legislative Branch through the Office of the County Auditor.
Purpose
The purpose of this engagement is to verify if the department’s construction and consultant contracts and contractual processes are effectively managed and comply with state and local regulations.
Performance Audit Definition
Performance audits provide objective analysis, findings, and conclusions to assist management and those charged with governance and oversight with, among other things, improving program performance and operations, reducing costs, facilitating decision-making by parties responsible for overseeing or initiating corrective action, and contributing to public accountability.
Our objective in performance auditing is to improve public services provided by county government. We do this by recommending specific actions that will address the issues we raised and by providing valuable information to the public, the administration, program leadership, the county council, and the mayor.
Objective
To evaluate if the Department of Public Works (DPW) effectively initiates and manages contracts, change orders, and supplemental agreements to completion promptly and within budget.
Scope
The scope of this audit included a review of construction and consultant contracts, change orders, and supplemental agreements managed by the Department of Public Works for Fiscal Years July 2017 through June 2022.
The audit was conducted from November 2021 to May 2023, with gaps in the audit process to perform other audit work and attend audit training courses.
We randomly sampled 20 out of 94 contracts (21%). We also reviewed nine Consultant contracts. Our review included contracts at various stages, from the pre-bid process to project closure.
Methodology
To accomplish our objective, we:
- Reviewed the department’s written policies and procedures
- Developed an understanding of the department’s internal control system, the bidding process, and applicable processes, practices, and document flows.
- Reviewed contracts, associated change orders, and supplemental agreements and reviewed a sampling of contracts and all related documents
- Assessed if contracts, change orders, and supplementals were in compliance with State statutes, County codes and policies, and other internal controls
- Determined when change orders or contract supplements were created, how costs to the contract were monitored, and cost documentation was provided
- Determined why change orders or contract supplements were added to the project schedule and identified the overall impact on the project
- Determined if management received periodic reports/information that provided the leadership the ability to view and track the performance of active contracts and construction schedules
- Referenced A Guide to the Project Management Body of Knowledge (PMBOK), Sixth Edition
- Reviewed OCA 2008 CIP audit report
- Noted any exceptions and identified opportunities/areas for improvements
- Was mindful of potential fraud, waste, and abuse during the audit
We conducted this performance audit in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objective.
What is the primary function of the Department of Public Works?
The Department of Public Works (DPW) directs and administers departmental functions, programs, and activities for the public's health, safety, and environment through planning, design, construction, operation, and maintenance of the County's infrastructure. DPW also administers applicable Federal, State, and local laws and rules governing public works programs. Their mission is to build, operate, and maintain public infrastructure for the success and growth of Hawaiʻi County.
DPW is composed of six divisions:
What does the Department of Public Works’ six divisions do?
- Administration is responsible for the administration of all departmental functions. Provides clerical, technical, personnel, fiscal, community outreach, and public information support services to the divisions within the department.
- Administration-Contracts Section prepares and processes construction and consultant contracts for the County.
- Automotive is responsible for the repair and maintenance of all automotive and construction equipment of the County on an island-wide basis, except such equipment as may be more practically maintained by the department having control thereof as determined by the Chief Engineer and/or Director. Authorized to bill any department, agency, or special fund for supplies and services. Responsible for the department's island-wide fuel storage tanks and facilities.
- Building oversees the administration, reviews, coordination, and enforcement of building codes within the County of Hawaiʻi. Responsible for the repair and maintenance of County-owned buildings. Responsible for contracting building repair, renovation, and new facilities construction.
- Support Staff Provides overall administration of the division; reviews the adoption of new codes and policies; renders decisions on code issues; monitors finances and manpower needs of the division. Collects fees for permits issued.
- Inspection Receives, reviews, issues and provides inspections for building, plumbing and electrical permits to assure compliance with code requirements. Issues notices for and pursues Building code violations.
- Design/Maintenance Design and Engineering - Plans designs, and prepares contract documents and bids for construction on County-owned facilities that are under the Department of Public Works responsibility. Assists County agencies with CIP and maintenance programming.
- Repair and Maintenance - Provides for the maintenance and repairs of County-owned facilities that are under the Department of Public Works responsibility.
- General Services - Provides custodial, grounds, and minor building maintenance at assigned County offices and baseyards island-wide.
- Engineering is responsible for the planning, engineering, and implementation of highways, bridges, drainage, and similar types of civil engineering capital improvement projects. Administers County Ordinances under the division's purview such as grading, driveway, sidewalk, encroachment, flood hazard control, and street digging. Programs division's capital improvement and fuel tax projects, including Federal Aid projects funded by the FHWA, NRCS, or the Army Corps of Engineers.
- Highway maintains County roads and rights-of-way, including repair, construction, or other types of works to improve road conditions for the purpose of safety. Maintains bridges, flood control facilities, or areas, including drainage easements under County jurisdiction. Responds to emergencies as needed to clear roads and remove hazards to ensure the safety of agency personnel and the public.
- Traffic was established under the Department of Public Works under Chapter 2, Article 9, Section 2-41 of the Hawaiʻi County Code. The Division installs maintains, and repairs all traffic control facilities and devices and street lighting systems in compliance with Chapter 24 of the Hawaiʻi County Code. The Division is responsible for all traffic engineering for the County and maintaining a traffic education program.
What is the difference between a change order and a supplemental agreement?
-
Change orders are documents used to modify the specifications, schedule, or cost of a project after the contract has been signed. Change orders are typically used when unforeseen circumstances arise, when the client requests additional work, or when the project requirements change. They must be approved by both parties and become part of the original contract. Change orders can impact the project schedule, cost, and quality, so they should be carefully reviewed and managed.
The County defines the change order as a written order signed by the procurement officer, directing the contractor to make changes which the changes clause of the contract authorizes the chief procurement officer to order without the consent of the contractor.
-
Supplemental agreements (or supplementals), also known as addenda (or addenda), are additional documents that modify or supplement the original contract. They can be used to clarify the terms of the agreement, add new terms or conditions, or address any misunderstandings or issues that arise during the course of the project. Supplements are typically attached to the original contract and become part of the overall agreement.
While the County does not provide an explicit definition for a "supplemental agreement," an "addendum" refers to a written document that is issued during the solicitation period to incorporate changes to the solicitation documents. These changes are considered and may become an integral part of both the solicitation documents and the resulting contract.
Our audit of the construction and consultant contracts, change orders, and supplemental agreements at the Department of Public Works (DPW) Administration, Building, and Engineering Divisions found gaps in its management and operational practices.
The construction and consultant contract process involves a series of steps that ensure the successful completion of projects undertaken by County departments. DPW’s Administration Contracts Group holds the responsibility of setting up the construction contract bid process. To ensure a systematic and organized approach, they utilize a checklist document to monitor the progression of contracts, starting from the pre-bid phase all the way through to the contract closeout process. This checklist serves as a comprehensive tool for tracking and managing the various stages of contract development and execution. The following is the contract process as described by the department:
Contract Specifications
In the construction industry, consultant contracts are a crucial part of projects. The process of selecting consultants is regulated by state law, and it involves a selection committee that reviews all the applicants' submissions. The selected consultants are ranked based on project criteria, and the highest-scoring consultant is offered the contract.
Consultant Contract Selection Process
According to Hawaiʻi Revised Statutes, Section 103D-304 Hawaiʻi Public Procurement Code, consultants must apply to the County stating their services and experience. Then, a county selection committee reviews all the applicant submissions for their discipline. Once approved, the applicants are added to a list of disciplines for which they applied. When a department is looking for a consultant for one of its projects, the head of the purchasing agency will select three members from the selection committee, who will then select consultants from the discipline and associated list based on project criteria. The consultants are ranked based on their qualifications, experience, and expertise. The highest-scoring consultant is offered the contract, and if they decline, the next highest-ranked consultant is offered the contract.
Pre-Bid
The DPW Administration Contract Group receives a request to post a contract bidding opportunity on the Public | Purchase website. They sign a Statement of Attestation before posting the bid package, which includes the bid specifications and plans, bid deadline, intent to bid deadline, bid opening date, or if necessary, the bid opening date may be extended.
For contracts over $500,000, a pre-bid conference must be held. After the conference, contractors can post comments or questions on the County site as an addendum. The project team reviews and decides on the addendum's validity and the County's position, and the project engineer or contract supervisor/technician posts the information.
Bid Selection
Once all bids are received, they are logged to the bid results, and preselected witnesses review the results to select the winning bid, typically the lowest bidder. However, if a bidder uses unlicensed or suspended subcontractors or fails to provide a complete subcontractor list, they may not be selected. Disqualified bidders can protest, and the department reviews and responds to protests.
The Administration Contracts Group creates a line item in their contracts tracking database and begins creating a file folder in the County’s document library (Laserfiche), adding key documentation. They continue adding documentation to Laserfiche throughout the project.
Contract Assignment
Before the beginning of construction, contracts must be assigned to contractors who have successfully bid on the project. It is imperative that the contracts are routed and approved timely and accurately, and the awarding process is done correctly. A Certificate of Liability Insurance is also required to ensure that contractors have valid insurance.
Notice to Proceed
Once the contract is signed off and preconstruction activities are completed, the Notice to Proceed letter is issued to the contractor.
Project Inspections
Project inspections ensure construction work is done according to the contract's specifications, plans, and codes.
- The Engineering Division coordinates with their Project Inspection Team's Supervisor to request a project inspector. The project inspector monitors subcontractors, testing soils, roadbeds, material usage, and deliveries.
- Building Division Project Coordinators periodically conduct on-site inspections and use either the contractor's or consultants’ construction inspection reports.
Invoice Processing
When the contractor invoices are received, the Engineering Inspectors and Building Project Coordinators ensure that the charges for the billing period are correct. The charges are verified based on the percentage of work performed or actual costs depending on the origin of the invoice.
Certified Payroll
Certified Payroll is monitored by Engineering Inspectors and Building Project Coordinators during the construction phase to ensure that contractors and subcontractors are paying the correct wages for hours worked. The wage rates are checked against the State's Prevailing Wages - Wage Rate Schedule.
Change Orders
Project change orders can be positive or negative and occur for a variety of reasons, including but not limited to:
- Errors in scoping or missed specifications
- Funding for bid alternatives or improvements
- Changes in equipment or materials needs
- Unforeseen issues
An acceptable range for change order costs is currently 10% to 15% of the original contract cost. Change orders can have a positive effect at times. For example, when federal funds become available to make unplanned but needed improvements where current projects are underway.
Project Management
Currently, the contractors develop project schedules, and both divisions use hardcopy project schedules. Project Managers, Engineers, and Project Coordinators track the project's progress and meet with the contractor as necessary.
Construction Closeout
The Administration Contracts Group oversees the closeout activities process and ensures all necessary closing documents are added to Laserfiche. The construction close-out documents include items such as draft letters, warranties, employment of residents, waivers of lien, and closing document acceptance, among others. Depending on the project type, documentation varies. Overall, the Contracts Administration Group plays a crucial role in the closeout activities.
Policies and Procedures
- The Engineering Division has established processes and procedures that assist both new and experienced engineers in navigating the engineering processes required for setting up and completing different types of projects they handle. However, the construction inspection teams lack policies and procedures.
- The Building Division project coordinators do not have policies and procedures.
Overview
Specifications refer to the detailed technical requirements and standards for the construction project. They provide specific instructions and guidelines for materials, methods, quality, and performance expectations. Specifications cover various aspects such as architectural, structural, electrical, plumbing, and mechanical requirements. They may include details about materials to be used, installation techniques, tolerances, testing procedures, and other specific technical criteria. Specifications ensure that the project is constructed to the desired standards and meets the design and performance expectations.
Inspecting aging facilities involves various and increasing risks: compromised structural integrity, outdated electrical systems, hazardous materials like asbestos, potential plumbing issues, environmental concerns, inadequate accessibility features, and fire safety deficiencies. To mitigate risks, the inspection process should include observations and findings in a detailed manner. This includes thorough descriptions, photographs, measurements, and supporting evidence, which collectively create a comprehensive record of the identified risks.
Audit Activity
To assess the appropriateness of the consultant selection process, we conducted a thorough review of 20 construction contracts as part of this audit. We selected seven consultant contracts that were affiliated with seven construction contracts. In two cases, there were separate contracts on file for different aspects of a project, resulting in a total of nine contracts. Additionally, we examined a representative sample of five contract specifications to evaluate the impact of errors in specifications on the effectiveness of project outcomes.
We evaluated the contract specifications against field orders and/or change orders to determine if they were incorrectly scoped or missing in the specifications. We also evaluated contracts to identify ambiguous descriptions or errors in Scope, Specifications, or Schedule of Values.
Furthermore, we evaluated whether appropriate documentation was provided for the contract's completeness, such as cost breakdown, drawings, designs, plans, specifications, insurance that reflects the proper coverage, and County boilerplate items. We also looked at state and county statutes, policies, and codes to ensure compliance.
During the review of the construction contracts, we observed that some change orders were created to address issues that could have been avoided if proper oversight had been exercised. In addition, some contract specifications did not include certain details that could have prevented the need for change orders.
Of the 20 contracts reviewed, 19 contained associated change orders. There were 56 change orders for 19 contracts. Five of the 20 contracts had some changes that could have been caught during the design phase, as enumerated below:
Audit Activity Continued:
The Department of Public Works (DPW) leveraged change orders in at least two projects, saving the County $3,990,857.23. While an accepted industry standard recognizes acceptable change orders from 10 - 15%, contract change orders reviewed ranged from -12.23% to 417.23% of the original contract amount.
During the 2008 audit, similar shortcomings were identified, highlighting the importance of thorough scoping to minimize the necessity for contract supplements and change orders. The department did not address this crucial aspect which has contributed to increased costs and project delays for the County.
Cause of the Condition
Insufficient collaboration between the Building Division and other stakeholders during the project's design phase resulted in unaddressed concerns and requirements. Additionally, inspections of existing facilities could have been enhanced to identify issues.
Effect of the Condition
Inaccurate contract specifications resulted in additional costs, delays, and disruptions to the construction projects.
Finding 1: Inconsistent Contract Specifications
Recommendation 1: Complete Contract Specifications
We recommend Building Division allocate more time for collaboration between the clients and consultants during the project's design phase. Building Division should also review its contract specifications to ensure that they include all necessary details to decrease the need for change orders. Additionally, inspections should be enhanced to identify issues associated with aging facilities.
Overview
According to Project Management Body of Knowledge (PMBOK) 12.3.2.4 Inspection - An inspection is a structured review of the work being performed by the contractor. This may involve a simple review of the deliverables or an actual physical review of the work itself. On a construction/engineering/infrastructure project, inspections involve walkthroughs of the site by both the buyer and the contractor to ensure a mutual understanding of the work in progress.
Onsite inspections allow for quality assurance by verifying that the construction work meets the required standards and specifications. Inspectors can assess the materials used, construction techniques employed, and adherence to safety regulations. By conducting inspections, potential issues or defects can be identified early on, ensuring that the project is built to the desired quality.
Audit Activity
To verify this section, we interviewed personnel and examined a sampling of 20 out of 94 contracts (21%). Our review included contracts at various stages, including bidding, construction contract award, approvals, certificate of liability insurance, invoicing, certified payroll, change orders, and project close-outs. It included contracts with open, closed, and canceled statuses.
We identified the following:
- Onsite Inspections - Project Coordinators within the Building Division cannot perform their onsite inspection tasks adequately because the assigned tasks do not allow them enough time to complete required inspections for multiple assigned projects. As a result, contractors are allowed to perform field inspections on their behalf. This increases the County’s risk exposure because contractors may have compromised objectivity, limited accountability, and potential conflicts of interest.
- Project Coordinators - Building Division is inconsistent with conducting onsite inspections regularly.
Project Coordinators depend on onsite inspectors' reports to confirm completed work. Construction contractors have a vested interest in the contractor’s profit margin. Consultant contractors have a vested interest in protecting their reputations. In either case, there is an increased risk that the contractor will have undue influence on the construction inspectors, and reports may be biased or inaccurate.
-
Construction Inspectors -
- The Building Division does not have Construction Inspectors.
- Although Engineering Division Construction Inspectors have work processes to demonstrate they perform inspections properly, they do not have written policies and procedures. See Recommendation 5: Establish Written Policies and Procedures for more information regarding this finding.
The department has grappled with the persistent issue of relying on non-County inspectors or contractors to track progress since at least 2008. This reliance has resulted in issues that continue to affect the department, including:
- Lack of project oversight and control over monitoring
- Inconsistencies and discrepancies in the quality of report details
- Decreases accountability and transparency in project management
This reliance hampers the department's ability to ensure efficient and effective project progress, affecting timely completion, quality control, and overall project outcomes.
Cause of the Condition
The Building Division’s Project Coordinators do not perform field inspections regularly.
Effect of the Condition
The Building Division depends on onsite inspectors who report to the primary contractor, increasing the risk that the county's assets may be jeopardized, and the work may not be done correctly.
Finding 2: Onsite Inspections not Performed Regularly
Recommendation 2: Conduct Onsite Inspections Regularly
We recommend that the Building Division hire construction inspectors and/or outsource to contract inspectors, requiring them to report directly to the County’s Building Division.
Overview
Certified payroll provides detailed information on wages, hours, and benefits for employees on government-funded construction projects, ensuring compliance with labor laws. Reviewing it verifies fair wages and benefits. Invoices break down work and costs, allowing verification of adherence to terms and scope. It helps control budgets, detect fraud, and ensure contractual compliance. Reviewing certified payroll and invoices ensures legal compliance, prevents fraud, and maintains financial transparency and accountability in construction projects.
Certified Payroll, as mandated by Chapter 104 of the Hawaiʻi Revised Statute (HRS) (Wages and Hours of Employees on Public Works Law), applies to all public works construction projects exceeding $2,000, regardless of procurement or financing method. The law requires contractors to submit certified copies of payrolls weekly to the contracting agency. Contractors are also responsible for providing certified payroll copies for subcontractors, certifying their accuracy, completeness, adherence to wage rates, and appropriate worker classifications. The Department of Labor and Industrial Relations (DLIR) and the contracting agency conduct investigations to ensure compliance, imposing penalties on contractors and subcontractors who violate the law.
Certified Weekly Payroll and Payroll Records
- A certified copy of all payrolls shall be submitted weekly to the contracting agency. [§104-3(a), HRS; §12-22-10, HAR]
- The contractor is responsible for the submission of certified copies of the payrolls of all subcontractors. The certification shall affirm that the payrolls are correct and complete, that the wage rates listed are not less than the applicable rates contained in the applicable wage rate schedule, and that the classifications for each laborer or mechanic conform with the work the laborer or mechanic performed. [§104-3(a), HRS; §12-22-10, HAR]
DLIR and the contracting agency will conduct investigations of contractors and subcontractors to ensure compliance with the law. If a contractor or subcontractor violates the law, the penalties are defined in §104-24, HRS.
Invoices, Payment for Goods and Services (HRS, §103-10)
Invoices and payments for goods/services: If a person provides goods or services to a state or county agency, they must be paid within 30 days. If there are unavoidable delays, the person is entitled to interest starting from the 30th day after delivery and ending when payment is made. This does not apply in disputes, labor disputes, power/mechanical failures, fires, acts of God, or similar circumstances beyond the control of the state/county. Payments below $25 may be made from agency petty cash funds, with exceptions granted by the comptroller. Payments made through state/county procurement cards follow specified contract terms.
Project Management Body of Knowledge (PMBOK)
- 7.4.1.4 Work Performance Data on project status, such as which costs have been authorized, incurred, invoiced, and paid.
- 4.3.3.2 Work Performance Data are the raw observations and measurements identified during activities to carry out the project. Data is often viewed as the lowest level of detail from which other processes derive information. Data is gathered through work execution and passed to the controlling processes for further analysis.
Audit Activity
To verify certified payroll, we met with the project teams to determine if they had a process to confirm that the primary contractor was appropriately paying the correct wages to their contractor and subcontractor employees and found:
- The Building Division’s Design and Engineering group lacks consistent practice for handling construction contractor-certified payroll, invoices, and documentation. This is due to the overwhelming workload and tasks they face, which forces them to find alternative methods to complete their work on time.
Specifically, our audit found:
- Certified Payroll
- On one project, there were multiple instances where the Building Division did not review certified payroll. Instead, the contractor received a transmittal stating the certified payroll was completed with a link to the certified payroll files; the files were never downloaded and no longer exist on the contractor’s website.
Additionally, since the Project Coordinators could not visit job sites regularly, they relied on the construction contractors’ field notes to help determine who was onsite during various pay periods.
-
The Engineering Construction Inspectors can visit job sites regularly and note the number of specific contractors/subcontractors onsite, which they match back to the certified payroll.
- On one project, there were multiple instances where the Building Division did not review certified payroll. Instead, the contractor received a transmittal stating the certified payroll was completed with a link to the certified payroll files; the files were never downloaded and no longer exist on the contractor’s website.
To verify invoices for a project, we reviewed and had discussions with the project teams to understand how invoices were verified. We also reviewed invoices for specific projects to trace the information to source data and found the following:
- Invoices
- Since the Project Coordinators could not visit job sites regularly, they would use field notes supplied by field inspectors employed by the contractor or consultant. Additionally, the Building Division does not always retain contractor invoicing documentation.
- The Engineering Construction Inspectors were able to visit job sites regularly, using field notes to document work materials received/work completed which provides the documentation for processing invoices.
Cause of the Condition
The Building Division’s Design and Engineering Group has no systematic process for managing certified payroll and invoices.
Effect of the Condition
Without a systematic process for managing certified payroll and invoices, there is an increased risk of inaccurate or delayed payments due to missing or lost evidence or documentation.
Finding 3: Certified Payroll and Invoices Not Reviewed
Recommendation 3: Review Certified Payroll and Invoices
We recommend the Building Division develop and document a systematic way of central processing, managing, and storing certified payroll and invoices documentation.
Overview
Project management software is a digital tool designed to assist individuals, teams, and organizations plan, organize, track, and collaborate on projects. It provides a centralized platform where project managers and team members can define project goals, create task lists, assign responsibilities, set deadlines, and track progress. Project management software typically offers features such as task management, scheduling, resource allocation, document sharing, communication tools, and reporting capabilities. Project management software helps to streamline project workflows, facilitate effective communication, helps optimize productivity, enhance coordination, and ensure successful project execution.
Audit Activity
To determine if DPW has a process of monitoring and tracking the status of projects and contracts, we corroborated with the appropriate staff and found the following:
- DPW does not have project management software.
- DPW has no management software tools that allow the Director and other designated staff to track department-wide activities and projects simultaneously.
- The lack of such software makes it hard to easily track key activities across the entire department. The administrative staff has the various division heads send manual reports with updates for all their projects.
The lack of a project management system has persisted as a challenge since at least 2008, further complicating the department’s workload management.
Cause of the Condition
DPW management has not actively pursued project management software to meet the needs of management and staff.
Effect of the Condition
The lack of project management software at DPW makes it difficult to track activities and projects, which results in an inefficient reporting process that requires manual updates from various department heads.
Finding 4: No Project Management Software
Recommendations 4: Use Project Management Software
We recommend DPW acquire project management software to improve tracking and managing the status of all their projects.
Overview
Standardizing work processes through establishing policies and procedures creates consistent guidelines, streamlines operations, enhances efficiency and improves productivity. Standardization reduces errors, inconsistencies, and duplication of efforts. It promotes clarity, transparency, and accountability among employees. Standardization facilitates knowledge sharing and cross-training and supports quality control by measuring performance and implementing corrective actions.
According to the PEMBOK 2.3 Organizational Assets and 2.3.1 Processes, Policies, and Procedures, the organizational process assets are the plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization. These assets influence the management of the project.
The department has consistently faced challenges regarding its policies and procedures, which were identified and outlined in the 2008 audit report. Neglecting the prioritization of policies and procedures has resulted in the department’s inability to effectively manage different aspects of its work processes, leading to decreased overall efficiency and productivity.
Audit Activity
To determine if DPW followed and enforced written policies and procedures, we gained an understanding of project management best practices, conducted site visits, corroborated with staff, observed operational practices and the control environment, and evaluated onboarding processes and procedures for new and existing professional staff and found:
- While the Administration Contracts Group has a seasoned staff and uses a contract checklist to ensure all processes are being completed timely, we noted that they do not have documented procedures for their work processes.
- The Engineering Inspection team does not have policies and procedures for their work processes. Their method for training new staff is to have them shadow a seasoned inspector “until they learn enough to be on their own.”
- The Building Division’s Design and Engineering group’s lack of policies and procedures since 2007 has resulted in employees independently developing and managing their work processes. This has led to various issues, including:
- Inconsistent documentation
- Unsound inspection practices
- Potentially bias inspection information provided by contractors
The Engineering Division has established processes and procedures that assist both new and experienced engineers in navigating the engineering processes required for setting up and completing different types of projects they handle. However, the construction inspection teams lack policies and procedures.
The Building Division’s project coordinators do not have policies and procedures to accomplish their tasks, and the project coordinators do not have standard work processes.
Cause of the Condition
The policies and procedures for managing and performing construction projects are incomplete.
Effect of the Condition
Not having written policies and procedures results in the following:
- Inefficiencies on projects leading to gaps in project management
- Inconsistency across projects
- Missing project documentation
- Staff confusion when taking on responsibilities for projects started by others
- Challenges in onboarding and training new staff due to a lack of clear guidelines and standardized processes
Finding 5: Incomplete Written Policies and Procedures
Recommendation 5: Establish Written Policies and Procedures
We recommend DPW Administration, Building Division, and Engineering Division’s Inspections group create or update policies and procedures for their work processes. Elements should include, but not be limited to:
- A standard format
- Distribution
- Version control
- Annual review/update
We recommend DPW Administration, Building, and Engineering divisions develop onboarding policies and procedures and ensure they use a standard creation, maintenance, and distribution process.
Overview
Lessons learned is a post-closing activity that occurs at the end of a project to assess successes and areas for improvement. The primary objective is identifying ways to prevent similar issues in future projects while capturing best practices. The project team convenes during the meeting to discuss the project's goals, objectives, and outcomes, as well as its achievements and challenges.
The team analyzes areas where they could have performed better and actively seeks solutions for encountered challenges. The success of the meeting hinges on open and honest communication, prioritizing learning from successes and failures rather than assigning blame. Ultimately, the lessons learned meeting is integral to the project management process by allowing the team to reflect, improve, and ensure future project success.
According to the Project Management Body of Knowledge 4.4.3.1 (PMBOK), the lessons learned register can include the category and description of the situation. The lessons learned register may also have the impact, recommendations, and proposed actions associated with the situation. The lessons learned register may record challenges, problems, realized risks and opportunities, or other content as appropriate.
The lessons learned register is created as an output of this process early in the project. After that, it is used as an input and updated as an output in many processes throughout the project. The persons or teams involved in the work also capture the lessons learned. Knowledge can be documented using videos, pictures, audio, or other suitable means to ensure the lessons' efficiency.
At the end of a project or phase, the information is transferred to an organizational process asset called a lessons-learned repository.
According to PMBOK 4.7, the close project or phase is finalizing all activities for the project, phase, or contract. The key benefits of this process are the project or phase information is archived, the planned work is completed, and organizational team resources are released to pursue new endeavors. This process is performed once or at predefined points in the project. The process's inputs, tools and techniques, and outputs are depicted in the data flow diagram.
Audit Activity
To determine if the Department of Public Works (DPW) has a lessons-learned process, we conducted site visits and corroborated with staff and found the Building and Engineering Divisions did not have formalized lessons-learned processes and documentation.
Not performing a thorough review of project outcomes and documenting lessons learned during project closeout puts a division at risk of repeating the same mistakes and encountering the same challenges in future projects, which can lead to delays, cost overruns, and, potentially, project failure.
Cause of the Condition
Building and Engineering divisions have not established a formal lesson-learned process.
Effect of the Condition
Not performing lessons learned at the end of each project can cause teams to repeat mistakes and make new mistakes in areas where they performed well. Conducting a lessons-learned process during a project is distinct from a post-project lessons-learned process because it does not provide a comprehensive overview of all issues and resolutions.
Finding 6: Lessons Learned Not Performed
Recommendation 6: Develop Lessons Learned Process
We recommend DPW develop a lessons-learned process where all project team members discuss the following:
- What went right
- What went wrong
- What needs to be improved
Following the meeting, the project manager or their designee should draft a report, disseminate it, and memorialize the outcomes for future projects. An example of a report could include:
- What went right/wrong
- Why it went right/wrong
- Is it worth avoiding/replicating in the future
- If so, how can this be done
Overview
A robust employee engagement strategy plays a vital role in creating a positive work environment that directly impacts an organization's ability to attract and retain top talent. By fostering a culture of commitment, motivation, and satisfaction, employee engagement becomes a catalyst for increased productivity, reduced turnover rates, and improved teamwork. Engaged employees invest their time and effort into their work, driving innovation and taking ownership of their responsibilities. Prioritizing employee engagement establishes a solid foundation for sustained growth, employee retention, and overall success, making the organization an attractive destination for talented individuals seeking fulfilling and rewarding careers.
According to Project Management Body of Knowledge PMBOK 9, Project Resource Management includes the processes to identify, acquire, and manage the resources needed for the successful completion of the project. These processes help ensure sufficient workforce capacities are available to the project manager and project team at the right time and place.
The 2008 audit outlined the deficiencies encountered by DPW as it relates to workforce capacity. The audit recommendations proposed methods to improve and delineate roles and responsibilities, including deadlines that, if enacted, would have improved recruitment and retention. The department neglected to fully implement all aspects of this recommendation requirement, which has contributed to its inability to meet its staffing needs.
Audit Activity
We reviewed position descriptions, organizational charts, and job postings to verify staffing. We interviewed Building and Engineering chiefs to determine if the Building Division’s Design and Engineering group was adequately staffed.
Both divisions face challenges in filling hard-to-fill positions, which DPW attributes to a salary package that is not competitive compared to market rates offered by the private sector.
The department faces severe challenges in recruiting and retaining staff, which has escalated to a crisis level. The situation is exacerbated by low employee morale, an excessive workload distributed among a limited staff, and the risk of losing critical knowledge due to the potential retirement of key employees. While the hiring practices fall under the responsibility of the human resources department, it is essential to acknowledge that resolving these issues extends beyond the department's control. Considering the current trajectory without timely intervention, there is a genuine concern that the department may become incapable of effectively operating.
The 2008 audit outlined the deficiencies encountered by DPW as it relates to staffing. Additionally, this review set a deadline to assess the department's performance and presented options. The department neglected to prioritize this crucial requirement and has been unable to address its needs.
Engineering Division:
As-of April 2023, the Engineering Division has challenges filling various hard-to-fill positions as noted below:
The Engineering Division has had recruitment, retention, and funding challenges, including eight positions and six vacancies. As a result of these challenges, they have had to rely on creative and less conventional recruitment methods.
Building Division
Given their time constraints, the Building Division’s Design and Engineering (D&E) Group’s Projects Coordinators (PC) have a demanding job with unreasonable expectations.
We reviewed of Building and Engineering Divisions' position descriptions and job classifications. The Project Coordinator's specifications are much more extensive, including but not limited to inspection and administrative work that is typically assigned to different classifications. The Project Coordinator's job responsibilities are too numerous and complex to be completed within the allocated time. As a result, the Project Coordinators have had to resort to developing creative ways to expedite their work, which is not a sustainable, long-term solution.
As of April 2023, the Building Division operates at 68% workforce capacity with 23 vacancies.
Cause of the Condition
The Building and Engineering Divisions have yet to thoroughly explore and execute strategies to attract and retain candidates for open positions.
Department of Public Works Human Resources representative has not reviewed the Project Coordinators position description since 2007.
Effect of the Condition
The lack of thorough exploration and execution of strategies to attract and retain candidates for positions has resulted in a persistent shortage of qualified personnel and prolonged vacancies. Further, the absence of a review of the Project Coordinator’s position has led to outdated job requirements and responsibilities, hindering the efficiency and effectiveness within the divisions.
Finding 7: Ineffective Workforce Strategy
Recommendation 7: Increase Workforce Outreach
We recommend the Building and Engineering Divisions work with the Department of Human Resources to recruit and retain positions consistent with the merit principle (HRS §76-1), including but not limited to evaluating:
- Employee benefits
- Competitive compensation packages
- Career development and growth opportunities
- Organizational culture
- Communication and transparency
- Employee mental health
- Recruitment efforts
Some items, such as compensation and benefits, are covered under collective bargaining agreements. This recommendation is not meant to suggest that the County of Hawaiʻi should exceed its legal authorities, but rather that it should work to holistically bolster the initial and ongoing overall value an employee perceives from their employment, referred to as “Total Compensation.”
Additionally, we recommend the Building Division work with Human Resources to review the Project Coordinators' position description and make changes where necessary.
As a practice, we remain mindful and document instances of fraud, waste, and abuse within the scope of the audit objective and not specifically Countywide.
Management reported no fraud, ongoing investigations, and pending litigation that may impact this audit.
During the Audit, we did not observe the Department of Public Works deliberately engaged in wasteful practices. However, our findings indicate that inefficiencies within the department have resulted in the discovery of wasteful practices, as duly identified and documented throughout the report.
The Office of the County Auditor has concluded its audit with the Department of Public Works’ (DPW) Building and Engineering Division’s construction contracts, change orders, and supplements. Our review has led us to make seven recommendations.
When our recommendations are implemented in good faith, the department can expect the following benefit:
Complete Contract Specifications
1. Completing contract specifications can help identify and address any unaddressed concerns and requirements before the construction phase begins. Additionally, identifying existing issues that may arise within aging County facilities may help to avoid costly change orders during construction.
Conduct Onsite Inspections Regularly
2. Hiring construction inspectors or contract constructions inspectors who report directly to the County’s Building Division increases assurance that our assets are being protected.
Review Certified Payroll and Invoices
3. Processing, managing, and centrally storing documentation for invoices and certified payroll will ensure all appropriate information has been processed and documented in the event the Building Division’s Design and Engineering group needs to access and retrieve information for any issues.
Use Project Management Software
4. Implementing this recommendation will provide DPW management and project teams the opportunity to track projects at the aggregate and project level. It would also provide the management teams with the ability to provide additional management oversight.
Establish Written Policies and Procedures
5. Implementing policies and procedures will provide a logical way to:
- Manage projects
- Maintain consistency across projects
- Manage documentation
- Assume responsibility for projects that were started by other staff members
- Use policies and procedures can also be used for training and guidance of new staff.
Develop Lessons Learned Process
6. The benefits of implementing this recommendation are that the project teams can identify their strengths and weaknesses and use the information gained from the Lessons Learned process to continuously improve their weaknesses and strengthen areas where they are already performing well.
Increase Workforce Outreach
7. Recruiting and retaining positions consistent with the merit principle enhances overall value perceived by employees in their employment with the County.
In closing, to improve government accountability and ensure audit recommendations are implemented or resolved, we will continuously monitor the status of recommendations using our remediation tracker. To view the department’s status, visit us at: https://www.Hawaiʻicounty.gov/our-county/legislative/office-of-the-county-auditor.
Management has verbally committed to providing a response as a supplemental after publication of this report.